Question: 1 pts An activity on a PERT network has these time estimates: optimistic = 1 , most likely = 4 , and pessimistic = 7
pts
An activity on a PERT network has these time estimates: optimistic most likely and pessimistic Its expected time and variance if it is a critical activity
;
none of these
;
:
;
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
