Question: 1 pts Question 44 The activity. Manage the project scope, schedule, budget, and people to ensure the project achieves its goal is conducted in which

1 pts Question 44 The activity. "Manage the
1 pts Question 44 The activity. "Manage the project scope, schedule, budget, and people to ensure the project achieves its goal is conducted in which phase of the project life cycle? define project goal O evaluate project O execute project plan plan project close project 1 pts Question 45 The knowledge area of the PMBOK that unifies and coordinates the other knowledge areas is O Quality management Integration management Scope management Stakeholder management Communications management