Question: Question 5 A project is planned for twelve months at the total cost of $ 1 2 0 , 0 0 0 , which will

Question 5
A project is planned for twelve months at the total cost of $120,000, which will be spent equally over the periods. It is now month 4 and your projects CPI is .9091 and its SV is $10,000. How is the project performing?
1 point
Over budget and behind schedule
Under budget and ahead of schedule
Under budget and behind schedule
Over budget and ahead of schedule