Question: 1 . Question 1 As a project manager, you encounter a problem that will affect the project delivery date. You need to raise the issue

1.
Question 1
As a project manager, you encounter a problem that will affect the project delivery date. You need to raise the issue to project stakeholders. How should you best communicate the problem to stakeholders?
1 point
Provide stakeholders with a short summary and proposed solution to the problem.
Send stakeholders a link to the project plan with the problem highlighted.
Email stakeholders outlining the problem in detail and ask how they would like to proceed.
Add stakeholders to an ongoing email chain to provide them with context for the problem.
2.
Question 2
As a project manager, you need to synthesize information about a problem to stakeholders. What should you do first in your synthesizing process?
1 point
Reread documents from previous projects.
Reread the project plan.
Make a list of steps to complete.
Gather information from multiple sources.
3.
Question 3
OKRs are a tool used for what?
1 point
Project management workflows
A summary of the project
A brief plan for the project
Organization-wide goal setting
4.
Question 4
You have synthesized the information around a problem you encountered in your project. You are now ready to communicate the problem to your stakeholders. Which of the following best describes how OKRs can help persuade your stakeholder to take the problem seriously?
1 point
You can present how your proposed solution addresses key results of a company OKR.
You can present how the problem reveals weaknesses in the companys OKRs.
You can present how the original project goals fail to align with the companys OKRs.
You can suggest a new OKR that your stakeholder may present to their companys CEO.
5.
Question 5
As a project manager, what should you consider before writing an email to a stakeholder to communicate an issue? Select all that apply.
1 point
How the project will affect you and the stakeholders
What is most important to a stakeholder
How the problem will affect the company as a whole
What is most important to the project team
6.
Question 6
You are writing the closeout report for a project you are managing. You observe that your project plan called for an $80,000 budget, but actual costs totaled $87,500. You note how the majority of extra costs were due to unexpected increases in the price of materials. Which part of your closeout report is the best place to document this information?
1 point
The outcomes section
The lessons learned section
The project documentation archive
The performance baseline section
7.
Question 7
What is the purpose of the executive summary in an impact report?
1 point
To show senior stakeholders that all the tasks were completed
To show senior stakeholders a performance overview of the project
To allow senior stakeholders to give the team feedback on the project
To give senior stakeholders a concise description of positive outcomes within the project
8.
Question 8
Which of the following describes the audience of your project impact report?
1 point
Project team members and vendors who made essential contributions to the projects final outcome
Senior stakeholders or project sponsors who were not involved in the day-to-day details of the project
Future project managers or other readers interested in your projects details
Potential employers interested in your ability to synthesize and communicate information clearly

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!