Question: 1 . Request for proposal: a . The project - functional interface definition is poor. 2 . Submittal to Customer: a . The work breakdown

1. Request for proposal:
a. The project-functional interface definition is poor.
2. Submittal to Customer:
a. The work breakdown structure is poorly defined.
3. Contract award:
a. Engineering does not request manufacturing input for end-item production.
4. Design review meetings:
a. Improper systems integrations have created conflicts and communication break down.
b. Several functional managers did not realize that they were responsible for certain risks.
c. The impact of design changes is not systematically evaluated.
5. Testing the product:
a. Time and cost constraints are not compatible with the state of the art.
6. Customer acceptance:
a. The customer does not fully realize the impact that a technical change will have upon cost and schedule.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!