Question: 1. Suppose we have a complete activity predecessor table (shown below) and we wish to create a network diagram highlighting the activity sequence for this
1. Suppose we have a complete activity predecessor table (shown below) and we wish to create a network diagram highlighting the activity sequence for this project. Using MS Project, enter the activities and their predecessors and create a complete activity network diagram for this project.
ProjectRemodeling an Appliance Activity Predecessors
A. Conduct competitive analysis
B. Review field sales reports
C. Conduct tech capabilities assessment
D. Develop focus group data A, B, C
E. Conduct telephone surveys D
F. Identify relevant specification improvements E
G. Interface with marketing staff F
H. Develop engineering specifications G
I. Check and debug designs H
J. Develop testing protocol G
K. Identify critical performance levels J
L. Assess and modify product components I, K
M. Conduct capabilities assessment L
N. Identify selection criteria M
O. Develop RFQ M P. Develop production master schedule N, O
Q. Liaison with sales staff P
R. Prepare product launch