Suppose we have a complete activity predecessor table (shown here) and we wish to create a network diagram highlighting the activity sequence for this project. Using MS Project, enter the activities and their predecessors and create a complete activity network diagram for this project. ProjectRemodeling an Appliance

Activity Predecessors

A Conduct competitive analysis

B Review field sales reports

C Conduct tech capabilities assessment

D Develop focus group data A, B, C

E Conduct telephone surveys D

F Identify relevant specification improvements E

G Interface with marketing staff F

H Develop engineering specifications G

I Check and debug designs H

J Develop testing protocol G

K Identify critical performance levels J

L Assess and modify product components I, K

M Conduct capabilities assessment L

N Identify selection criteria M

O Develop RFQ M

P Develop production master schedule N, O

Q Liaise with sales staff P

R Prepare product launch Q

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!