Question: Suppose we have a complete activity predecessor table (shown here) and we wish to create a network diagram highlighting the activity sequence for this project.
Suppose we have a complete activity predecessor table (shown here) and we wish to create a network diagram highlighting the activity sequence for this project. Using MS Project, enter the activities and their predecessors and create a complete activity network diagram for this project. ProjectRemodeling an Appliance
Activity Predecessors
A Conduct competitive analysis
B Review field sales reports
C Conduct tech capabilities assessment
D Develop focus group data A, B, C
E Conduct telephone surveys D
F Identify relevant specification improvements E
G Interface with marketing staff F
H Develop engineering specifications G
I Check and debug designs H
J Develop testing protocol G
K Identify critical performance levels J
L Assess and modify product components I, K
M Conduct capabilities assessment L
N Identify selection criteria M
O Develop RFQ M
P Develop production master schedule N, O
Q Liaise with sales staff P
R Prepare product launch Q
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts