Question: Suppose we have a complete activity predecessor table below and we wish to create a network diagram highlighting the activity sequence for this project. Using
Suppose we have a complete activity predecessor table below and we wish to create a network diagram highlighting the activity sequence for this project. Using MS Project, enter activities A through E their durations, and their predecessors. What is the critical path and the total duration for the project? Note that all duration times are in days.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
