Question: 1. Task time estimates for the modification of an assembly line at Jim Goodales Carbondale, Illinois, factory are as follows: Activity Time (in hours) Immediate
1. Task time estimates for the modification of an assembly line at Jim Goodales Carbondale, Illinois, factory are as follows:
| Activity | Time (in hours) | Immediate Predecessors |
| A | 6 | -- |
| B | 7 | -- |
| C | 5 | A |
| D | 8 | B, C |
| E | 5 | B, C |
| F | 8 | D |
| G | 4 | E, F |
- Draw the project network using AON.
- Identify the critical path.
- What is the expected project length?
- Create a gantt chart for the project.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts