Question: just need to know the slack activity ! Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are
just need to know the slack activity !
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: The precedence diagram for the project is shown in What would be the Slack for Activity G? A. 4 B. 6 C. 5 D. 2 E. 0