Question: 1. The expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 6. What is the
1. The expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 6. What is the probability that the project will (a) require at least 17 months? (b) be completed within 20 months (c) require at least 23 months? (d) be completed within 25 months?Problem 7-22 Mean (months) Variance (months^2) Standard deviation (months) (a) P(need >= 17 months) = (b) P(need <= 20 months) = (c) P(need >= 23 months) = (d) P(need <= 25 months) =
| Problem 7-22 | |||
| Mean (months) | |||
| Variance (months^2) | |||
| Standard deviation (months) | |||
| (a) P(need >= 17 months) = | |||
| (b) P(need <= 20 months) = | |||
| (c) P(need >= 23 months) = | |||
| (d) P(need <= 25 months) = |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock