Question: Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21months, and the

Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21months, and the project variance is 9.

a) The probability that the project will be completed in 12 months (round to 4 decimal places) b) The probability that the project will be completed in 20 months =

(round your response to four decimal places).

B) The due date that yields a 95% chance of completion =

months (round your response to two decimal places).

PLEASE, Explain STEP By Step. how to solve this, this is. a study guide, and it will benefit me a lot, Thank you!

Using PERT, Adam Munson was able to determine that the expected project

Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 9 . a) The probability that the project will be completed in 12 months = (round your response to four decimal places)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!