Question: Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 2 4 months,

Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 16. The probability that the project will be completed in 28 months = Plz explain !!Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a
pleasure yacht is 21 months, and the project variance is 9.
a) The probability that the project will be completed in 12 months =0.0013(round your response to four
decimal places).
b) The probability that the project will be completed in 20 months =0.3694(round your response to four
decimal places).
c) The probability that the project will be completed in 24 months =,(round your response to four decimal places).
 Using PERT, Adam Munson was able to determine that the expected

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!