Question: Hey draw project network - compute the early and late activity and identify the critical path; Answer is highly appreciated: Give answer ASAP The project
Hey
draw project network - compute the early and late activity and identify the critical path; Answer is highly appreciated:

Give answer ASAP
The project information for the custom order project of the Air Control Company is presented here. Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical path. ID Description Predecessor Time A Order review None 2 B Order standard parts 3 Produce standard parts A 10 D Design custom parts A 13 E Software development A 18 F Manufacture custom hardware CD 15 G Assemble BF 10 H Test E, G 5Step by Step Solution