Question: 1. The probability that the project will finish at least 2 days early 2. The probability that the project will finish at least 2 days

1. The probability that the project will finish
1. The probability that the project will finish at least 2 days early
2. The probability that the project will finish at least 2 days late.
Duration Optimistic (T.) Most Likely (Tm) Expected Duration (T) Pessimistic (Tp) Standard Deviation (0) Activity Variance Ve = 02 4 DO 2 5 4 2 7 6 2 10 7 14 8 2 21 4.167 8.500 6.000 2.000 11.333 TE= 32 0.833 0.694 1.500 2.250 0.667 0.444 0 0 2.333 5.444 Ve=8.833