Question: In a CPM network, the critical path has five activities. Their durations are tabulated next. Duration (Days) Most Likely (Tm) Activity Optimistic (TJ Pessimistic (p)

In a CPM network, the critical path has five activities. Their durations are tabulated next. Duration (Days) Most Likely (Tm) Activity Optimistic (TJ Pessimistic (p) 2 B D E 5 4 2 7 4 8 6 2. 10 7 14 8 2 21 Compute the following nine values: 1. The probability that the project will finish by the end of day 32 2. The probability that the project will finish by the end of day 34 3. The probability that the project will finish before day 30 4. The probability that the project will finish on the 32nd day 5. The probability that the project will finish no later than the 35th day 6. The probability that the project will finish at least 2 days early 7. The probability that the project will finish at least 2 days late 8. The probability that the project will finish on the 32nd day 1 day 9. The completion date with at least a 90% confidence level
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
