Question: 1. Use the data to calculate the earned value for the project. All amounts are in thousands of dollars Select one: a. ( $ 38,850
1. Use the data to calculate the earned value for the project. All amounts are in thousands of dollars Select one: a. \\( \\$ 38,850 \\) b. \\( \\$ 100,000 \\) c. \\( \\$ 454,750 \\) d. \\( \\$ 43,250 \\)