Question: Use the data to calculate the eamed value for the project. All amounts are in thousands of dollars. Duration (weeks) 10 15 20 25 %


Use the data to calculate the eamed value for the project. All amounts are in thousands of dollars. Duration (weeks) 10 15 20 25 % Comp Conceptual Design 10 6 100% Graphics Design 6 75% Copyright 4 Un 6 6 15% Samples 4 25% Tooling 6 4 (10% Production 6 10% Total 10 vo Cumulative 50 76 100 Select one: a $454,750 b. $38,850 OC $43,250 O d. $100,00 en 16 Crashing a project should occur: ca