Question: 1 . Use the information below to develop a schedule for the project. Assume the resource pool is limited to SIX. Schedule using the following

1. Use the information below to develop a schedule for the project. Assume the resource pool is limited to SIX. Schedule using the following heuristics :
(i) Minimum Slack
(ii) Shortest Job First
(iii) Maximum Resource Required First
List the activities in the order in which you schedule them.
Which activities are Critical ?
What is the Project Duration ?
What is the efficiency of your schedule ?
ACTIVITY DURATION RESOURCE
1-232
1-343
1-421
2-522
2-652
3-731
4-713
4-842
5-911
6-724
6-942
7-1034
8-1021
9-1035

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!