Question: 1 . Use the information below to develop a schedule for the project. Assume the resource pool is limited to SIX. Schedule using the following
Use the information below to develop a schedule for the project. Assume the resource pool is limited to SIX. Schedule using the following heuristics :
i Minimum Slack
ii Shortest Job First
iii Maximum Resource Required First
List the activities in the order in which you schedule them.
Which activities are Critical
What is the Project Duration
What is the efficiency of your schedule
ACTIVITY DURATION RESOURCE
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
