Question: 1. Use the information below to develop a schedule for the project. Assume the resource pool is limited to SIX. Schedule using the following heuristics
1. Use the information below to develop a schedule for the project. Assume the resource pool is limited to SIX. Schedule using the following heuristics :
(i) Minimum Slack First
(ii) Shortest Job First
(iii) Maximum Resource Required First List the activities in the order in which you schedule them. Which activities are critical ? What is the Project Duration ? What is the efficiency of your schedule ?
| ACTIVITY | DURATION | RESOURCE |
| 1-2 | 3 | 2 |
| 1-3 | 4 | 3 |
| 1-4 | 2 | 1 |
| 2-5 | 2 | 2 |
| 2-6 | 5 | 2 |
| 3-7 | 3 | 1 |
| 4-7 | 1 | 3 |
| 4-8 | 4 | 2 |
| 5-9 | 1 | 1 |
| 6-7 | 2 | 4 |
| 6-9 | 4 | 2 |
| 7-10 | 3 | 4 |
| 8-10 | 2 | 1 |
| 9-10 | 3 | 5 |