Question: Use the information below to develop a schedule for the project. Assume the resource pool is limited to SIX . Schedule using the following heuristics
- Use the information below to develop a schedule for the project. Assume the resource pool is limited to SIX. Schedule using the following heuristics :
- Minimum Slack First
- Shortest Job First
- Maximum Resource Required First
List the activities in the order in which you schedule them.
Which activities are critical ?
What is the Project Duration ?
What is the efficiency of your schedule ?
| ACTIVITY | DURATION | RESOURCE |
| 1-2 | 3 | 2 |
| 1-3 | 4 | 3 |
| 1-4 | 2 | 1 |
| 2-5 | 2 | 2 |
| 2-6 | 5 | 2 |
| 3-7 | 3 | 1 |
| 4-7 | 1 | 3 |
| 4-8 | 4 | 2 |
| 5-9 | 1 | 1 |
| 6-7 | 2 | 4 |
| 6-9 | 4 | 2 |
| 7-10 | 3 | 4 |
| 8-10 | 2 | 1 |
| 9-10 | 3 | 5 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
