Question: Use the information below to develop a schedule for the project. Assume the resource pool is limited to SIX . Schedule using the following heuristics

  1. Use the information below to develop a schedule for the project. Assume the resource pool is limited to SIX. Schedule using the following heuristics :
  2. Minimum Slack First
  3. Shortest Job First
  4. Maximum Resource Required First

List the activities in the order in which you schedule them.

Which activities are critical ?

What is the Project Duration ?

What is the efficiency of your schedule ?

ACTIVITY DURATION RESOURCE
1-2 3 2
1-3 4 3
1-4 2 1
2-5 2 2
2-6 5 2
3-7 3 1
4-7 1 3
4-8 4 2
5-9 1 1
6-7 2 4
6-9 4 2
7-10 3 4
8-10 2 1
9-10 3 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!