Question: 1. Use the information from the table provided and develop a project network. Complete the forward and backward pass. What is the critical path? How

1. Use the information from the table provided

1. Use the information from the table provided and develop a project network. Complete the forward and backward pass. What is the critical path? How many days will the project take? ID Description Predecessor Time A Survey site None 2 B Excavate site A 4 B 3 Install power lines Install drainage D B 5 E Pour foundation CD 3