Question: 1- Using PERT, if an activity has a positive slack it means that this activity is on the Critical Path. Cannot be delayed without delaying
1- Using PERT, if an activity has a positive slack it means that this activity
- is on the Critical Path.
- Cannot be delayed without delaying the project.
- Can be delayed.
- Is the most expensive activity.