Question: 1. Using the data in Table 1, Draw the network, b. Determine the total project duration; c. Determine the critical path; d. Determine the slack

1. Using the data in Table 1, Draw the network, b. Determine the total project duration; c. Determine the critical path; d. Determine the slack of activities not on the critical path, and e. Determine the probability of completing the project in 45 days or less.

1. Using the data in Table 1, Draw the network,

Table 1 Time Estimates Activity o m Precedence A B D E O O O N 00 6 10 15 6 9 14 A 8 12 20 A 5 8 13 B 7 11 17 8 14 18 DE w DI