Question: 1) what is the bottle neck process? 2) what is the throughput for the overall system? 3) if the firm operates 9 hours/day , 20

1) what is the bottle neck process? 2) what is the throughput for the overall system?
3) if the firm operates 9 hours/day , 20 days per month, what is the monthly capacity of this manufacturing system? 4) Hossein retains the drilling work and the time for the operations drops 5 minutes per unit. What is the new bottle neck? 5) How many units per month can the system now make? 6) what is the throughput time now?
Scenario: Naji Manufacturing's CEO, Hossein Naji, is analyzing his furniture manufacturing system seen above. The Drill operation occurs separately from, and simultaneously with, the Cutting and Bending operations. The product only needs to go to one of the three Packing operations that are in parallelStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts