Question: 1. What is the current critical path? 2. Which activity to crash first? 3. After crashing 1 week, what is the new critical path(s)? 4.

1. What is the current critical path? 2. Which1. What is the current critical path? 2. Which

1. What is the current critical path? 2. Which activity to crash first? 3. After crashing 1 week, what is the new critical path(s)? 4. Which activity or activities to crash then? 5. What is the total cost? Activity Crash Cost/week ($) Max Crash Possible (weeks) A 2 $115,000 $95,000 2 D o E 2 $50,000 $40,000 F 1 23 34 24/35 Legend: ESEP G O LS LF F (11) $80,000 $100,000 9 123 9 123 35 42 35 42 0 A (9) C (14) G (7) 09 D (10) E (12) 9 119 1121 1 (8) 2335 23 35 42 50 4250 H (21) 1940 21 42