Question: 1. What is the difference between BAC, ETC, and EAC? 2. In month 9 the following project information is available: actual cost is $2,000, earned

1. What is the difference between BAC, ETC, and EAC?

2. In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and the planned cost is $2,400. Compute the SV and CV for the project.

3. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?

Please provide at least 300 words with sporting calculations.