Question: 1. What is the difference between BAC, ETC, and EAC? 2. In month 9 the following project information is available: actual cost is $2,000, earned
1. What is the difference between BAC, ETC, and EAC?
2. In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and the planned cost is $2,400. Compute the SV and CV for the project.
3. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?
Please provide at least 300 words with sporting calculations.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
