Question: 1. what is the minimum completion time? A. 25 weeks B. 20 weeks C. 23 weeks D. 24 weejs 2.If Egon has a budget of

1. what is the minimum completion time?
A. 25 weeks B. 20 weeks C. 23 weeks D. 24 weejs
2.If Egon has a budget of only $3000 for crashing costs, what is the shortest possible completion time?
A. 28 weeks B. 26 weeks C. 29 weeks D. 27 weeks
3. How much will it cost Egon to reduce the original total project time by six weeks?
A. $2,900 B. $3,850 C. $2,100 D. $4,850
4. How much did crashing that last (sixth) week cost Egon?
A. $1,250 B. $750 C. $1,500 D. $1000