Question: 1. What is the project completion date? 2. What is the total cost required for completing this project on normal time? 3. If you wish

1. What is the project completion date?
2. What is the total cost required for completing this project on normal time?
3. If you wish to reduce the time required to complete this project by 1-day, which activity should be crashed, and how much will this increase the total cost?
7. (15 points) Development of New Version of a particular business software project is being considered by J&J technology firm in Pomona, CA. The activities necessary for the completion of this project are listed in the following table: Crash Time (days) Normal Cost Crash Cost Activity Normal Time (days) 4 Immediate Predecessors 3 $2.000 $2,600 B 2 1 $2,200 $2,800 3 3 $500 $500 D 8 4 $2,300 $2,600 1 A 6 3 $900 $1.200 B 3 N $3,000 $4.200 G 4 2 $1,400 $2,000 DEStep by Step Solution
There are 3 Steps involved in it