Question: 1- Which activity has the largest slack? How much? 2- Indicate the critical path and the total project duration? 3-Crash the project by 3 days

1- Which activity has the largest slack? How much?

2- Indicate the critical path and the total project duration?

3-Crash the project by 3 days and re-identify the critical path?

4- If you delete activities K and M, what is the critical path? How many days do you save? Can you still crash the project by 3 days?

1- Which activity has the largest slack? How

Activity Predecessor (Letter) Predecessor (Number) Estimated Duration (Days) . 3 B 4 4 D A 1 3 E D 4 4 F E 5 3 G F 6 4 H F 6 5 1 G H 7,8 6 J G 7 3 K . 8 4 L I, K 9,11 5 . J 10 2