Question: 1 Which statement describes best why you should document assumptions? a Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows baseline adjustments
1 Which statement describes best why you should document assumptions?
a Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows baseline adjustments in case of project crisis.
b Assumption analysis is a valuable tool and technique to explore the validity of assumptions during risk identification.
c Assumptions limit the project management team's options for decision making because they can not be controlled by the team.
d In case of schedule or budget overruns, the documentation of assumptions supports a clear assignment of responsibility.
2 Which is normally not regarded as an element of cost of quality?
a Prevention costs
b Maintenance cost
c Appraisal costs
d Failure costs
3 You have recently been assigned as a project manager to a new B-O-T (build, operate, transfer)capital project. Reviewing the initial documentation you found out that it has been calculated with a very small margin during operations of its product for the shareholders. What should you do?
a As you are not responsible for lifecycle costing, you don't have to worry about operation profits. Focus on project costs from initiation through handover.
b Ensure maximum profits by buying the best and cheapest items, components and modulespotentially from a big number of different suppliersand integrating them.
c Create a realistic plan broken down to a sufficient level of detail. Perform all risk management processes. Ensure real-time communications with all stakeholders.
d Try to get a second project manager assigned to share decision making and accountability to shareholders with the person
4 A project is handled by departments of an organization and expedited by a project coordinator. Which of the following statements is most likely to be true?
a The performing organization is a weak matrix.
b The performing organization is doing "management by projects".
c The performing organization is a strong matrix.
d The performing organization is projectized.