Question: 1 . You determine that a planned feature is not technically feasible. You eliminate the feature from the project. A , B , C ,

1. You determine that a planned feature is not technically feasible. You eliminate the feature from the project.
A, B, C, D, E, F, G
2. You can get a 10% discount from a key supplier if you order 100,000 units. Your project requires 80,000 units. You contact other Project Managers to determine if there are needs for the additional units to gain the discount.
A, B, C, D, E, F, G
3. There is an opportunity to save $10,000 from a sellers offer. Your team agrees that the offer is good.
A, B, C, D, E, F, G
4. You learn of an opportunity to cut three weeks off your project schedule. Resources are available that allow you to crash key critical activities to increase the probability of achieving the time savings.
A, B, C, D, E, F, G
5. Your team does not have the expertise to eliminate a key safety risk. You spend $10,000 to enlist the support of a third party vendor who will respond to the risk.
A, B, C, D, E, F, G
6. There are key risks to your project schedule. You develop a training program to respond to the first risk. For the second you develop a prototype which will correct the problem.
A, B, C, D, E, F, G
7. You add an additional vendor at a cost of $25,000 with the expertise to ensure an identified risk event occurs that will lead to opportunities to reduce time spent on critical path activities.
A, B, C, D, E, F, G
Word Bank
A. Share
B. Avoid
C. Enhance
D. Accept
E. Transfer
F. Mitigate
G. Exploit

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!