Question: 10 7, 10, 12 7, 10, 13 A PERT network for a project is shown below: a. Find the expected duration of each activity.

10 7, 10, 12 7, 10, 13 A PERT network for a project is shown below: a. Find the expected duration of each activity. b. Find the expected duration of the critical path. c. Find the critical path. d. Find the slack at each node. 20 30 9, 11, 13 8, 14, 20 6, 15, 21 40 50 12, 15, 17 5, 9, 15 6, 10, 16 70 60 7, 9, 13 3,7,11 80 12, 16, 25 9, 15, 18 90
Step by Step Solution
There are 3 Steps involved in it
To answer these questions well go through each one step by step a Find the expected duration of each ... View full answer