Question: Olsen Company prepared the following PERT network for a project, with expected time shown in days: Required: (1) Identify the critical path. (2) Determine the
.png)
Required:
(1) Identify the critical path.
(2) Determine the slack time at each event.
7 2 Finish Start 9 10 8 13
Step by Step Solution
3.44 Rating (163 Votes )
There are 3 Steps involved in it
1 2 Event Earliest Expected Time Latest Allowable Time Slack Time 1 0 0 0 ... View full answer