Question: Olsen Company prepared the following PERT network for a project, with expected time shown in days: Required: (1) Identify the critical path. (2) Determine the

Olsen Company prepared the following PERT network for a project, with expected time shown in days:
Olsen Company prepared the following PERT network for a project,

Required:
(1) Identify the critical path.
(2) Determine the slack time at each event.

7 2 Finish Start 9 10 8 13

Step by Step Solution

3.44 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 2 Event Earliest Expected Time Latest Allowable Time Slack Time 1 0 0 0 ... View full answer