Question: 10 Activity Immediate Predecessors Normal Cost ($) Crash Cost ($) A B D E F G Normal Time (weeks) 8 3 7 3 3 6

10 Activity Immediate Predecessors Normal Cost

10 Activity Immediate Predecessors Normal Cost ($) Crash Cost ($) A B D E F G Normal Time (weeks) 8 3 7 3 3 6 2 Crash Time (weeks) 6 2. 2 5 1 2 AB 4000 2000 2000 3000 1000 2000 1500 6000 2500 3000 3500 1500 3500 2500 D EF 4 1 Given the information in the table, What will be the cost of crashing the time of the project to 17 weeks? (4 Points) Enter your