Question: Consider a project with the following information. Activity Immediate predecessors Normal time Crash time A B D E A A 10 12 11 26 5

Consider a project with the following

Consider a project with the following information. Activity Immediate predecessors Normal time Crash time A B D E A A 10 12 11 26 5 8 11 10 8 3 Crash cost per period $200 $300 $150 $260 $240 B, C What is the total cost of crashing the project by 2 time unit(s)