Question: 10. Develop the network diagram for the project below. Find the early, late and slack times for each activity. Identify and state the critical
10. Develop the network diagram for the project below. Find the early, late and slack times for each activity. Identify and state the critical path. [20] Activit Duratio Finish-to-Start Finish-to- Additional Lag Lag y n (days) Predecessor Start Lag Relationships A 5 None 0 None 0 B 10 A 0 None 0 C 15 A 0 None 0 D 5 B 5 Finish-Finish D to E 25 E 20 B 0 Finish-Finish E to F 0 F 15 D 0 None 0 G 10 C 10 Finish-Finish G to F 10 H 20 F 0 None 0