Question: Develop the network diagram for the project below. Find the early, late and slack times for each activity. Identify and state the critical path. [
Develop the network diagram for the project below. Find the early, late and slack times for each activity. Identify and state the critical path.
tableActivitytableDurationdaystableFinishtoStartPredecessortableFinishtoStart LagtableAdditional LagRelationshipsLagANone,None,BANone,CANone,DBFinishFinish to BFinishFinish to DNone,GCFinishFinish to FNone,