Question: Question 2 [20 marks] e) Develop the network diagram for the project below. Find the early, late and slack times for each activity. Identify and

Question 2 [20 marks]

e) Develop the network diagram for the project below. Find the early, late and slack times for each activity. Identify and state the critical path.

Activity Duration (days) Finish-to-Start Predecessor Finish-to-Start Lag Additional Lag Relationships Lag
A 5 None 0 None 0
B 10 A 0 None 0
C 15 A 0 Start-Finish C to D 20
D 5 B 5

Start-Start D to E

Finish-Finish D to E

5

25

E 20 B 0 Finish-Finish E to F 0
F 15 D 0 None 0
G 10 C 10 Finish-Finish G to F 10
H 20 F 0 None 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!