Question: Question 2 [20 marks] e) Develop the network diagram for the project below. Find the early, late and slack times for each activity. Identify and
Question 2 [20 marks]
e) Develop the network diagram for the project below. Find the early, late and slack times for each activity. Identify and state the critical path.
| Activity | Duration (days) | Finish-to-Start Predecessor | Finish-to-Start Lag | Additional Lag Relationships | Lag |
| A | 5 | None | 0 | None | 0 |
| B | 10 | A | 0 | None | 0 |
| C | 15 | A | 0 | Start-Finish C to D | 20 |
| D | 5 | B | 5 | Start-Start D to E Finish-Finish D to E | 5 25 |
| E | 20 | B | 0 | Finish-Finish E to F | 0 |
| F | 15 | D | 0 | None | 0 |
| G | 10 | C | 10 | Finish-Finish G to F | 10 |
| H | 20 | F | 0 | None | 0 |