Question: 10) Using simple exponential smoothing, predict the demand for wheel nuts when the previous forecast was 42 units, actual demand was 40 units, and =
10) Using simple exponential smoothing, predict the demand for wheel nuts when the previous forecast was 42 units, actual demand was 40 units, and = .10