Question: 11-12: A time study in bolt and nut assembly has been done with the following results: begin{tabular}{|l|r|} hline 11. What is the overall normal time

 11-12: A time study in bolt and nut assembly has been

11-12: A time study in bolt and nut assembly has been done with the following results: \begin{tabular}{|l|r|} \hline 11. What is the overall normal time for the bolt and nut assembly? & 2pts \\ \hline 12.Thefirmallows3%personaltime,two15-ninutecoffeebreaks,and2%unavoidabledelays.Findthestandardtimeforthisactivity. & 3pts \\ \hline \end{tabular}