Question: 12.6 with a paragraph supporting ur answer. typed please 126 Draw the network and identify the critical path. Also calculate the earliest-latest starting and finishing

12.6 with a paragraph supporting ur answer. typed please
12.6 with a paragraph supporting ur answer. typed
126 Draw the network and identify the critical path. Also calculate the earliest-latest starting and finishing times for each activity: Activity Preceding Activity Time (Weeks) A 4 B 6 A,B 7 D B 8 E B 5 F 5 G D 7 H 8 D, E F,G,H I 4