Question: 13. This value represents the planned cost to complete the work that has been done. It is called the _________________ of the task (2 Points)

13. This value represents the planned cost to complete the work that has been done. It is called the _________________ of the task (2 Points) a) budgeted cost of work scheduled b) earned value c) budgeted cost of work performed