Question: Below is the Planned time - phased value ( PV ) of Dalron Construction project. Week 1 2 3 4 5 6 7 8 9

Below is the Planned time-phased value (PV) of Dalron Construction project.
Week
12345678910
Task 152520
Task 2510151515121082
Task 35101515753
Total
Cumulative
What is the total budgeted cost at completion (BAC) of Dalron Construction project?
Answer:
Question 73
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the budgeted cost at completion (BAC) of Task 1?
Answer:
Question 74
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the budgeted cost at completion (BAC) of Task 2?
Answer:
Question 75
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the budgeted cost at completion (BAC) of Task 3?
Answer:
Question 76
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the project planned value (PV) at the end of week 7?
Answer:
Question 77
Not yet answered
Marked out of 1.0
Flag question
Question text
This table represents the actual cost (AC) of Dalron Construction project.
Week
1234567
Task 152520
Task 251520
15
1512
Task 35101515
Total
Cumulative
What is the actual cost (AC) at the end of week 7?
Answer:
Question 78
Not yet answered
Marked out of 1.0
Flag question
Question text
At the end of week 7 the work was completed as follows:
Task 1 is 100% completed,
Task 2 is 80% completed and
Task 3 is 60% completed.
What is the total earned value (EV) at the end of week 7?
Answer:
Question 79
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the CV [Cost Variance] at the end of week 7?
Answer:
Question 80
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the SV [Schedule Variance] at the end of week 7?
Answer:
Question 81
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the CPI [Cost Performance Index] at the end of week 7?
Answer:
Question 82
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the SPI [Schedule Performance Index] at the end of week 7?
Answer:
Question 83
Not yet answered
Marked out of 1.0
Flag question
Question text
Choose the right characteristic of the project based on your findings.
a.
The project is underbudget and behind schedule.
b.
The project is overbudget and behind schedule.
c.
The project is underbudget and ahead of schedule.
d.
The project is overbudget and ahead of schedule.
Question 84
Not yet answered
Marked out of 1.0
Flag question
Question text
The Dalron project is doing well, and no corrective action is needed?
Is it true or false?
Select one:
True
False
Previous activity
Jump to...
Jump to...

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!