Question: Below is the Planned time - phased value ( PV ) of Dalron Construction project. Week 1 2 3 4 5 6 7 8 9
Below is the Planned timephased value PV of Dalron Construction project.
Week
Task
Task
Task
Total
Cumulative
What is the total budgeted cost at completion BAC of Dalron Construction project?
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
What is the budgeted cost at completion BAC of Task
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
What is the budgeted cost at completion BAC of Task
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
What is the budgeted cost at completion BAC of Task
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
What is the project planned value PV at the end of week
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
This table represents the actual cost AC of Dalron Construction project.
Week
Task
Task
Task
Total
Cumulative
What is the actual cost AC at the end of week
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
At the end of week the work was completed as follows:
Task is completed,
Task is completed and
Task is completed.
What is the total earned value EV at the end of week
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
What is the CV Cost Variance at the end of week
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
What is the SV Schedule Variance at the end of week
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
What is the CPI Cost Performance Index at the end of week
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
What is the SPI Schedule Performance Index at the end of week
Answer:
Question
Not yet answered
Marked out of
Flag question
Question text
Choose the right characteristic of the project based on your findings.
a
The project is overbudget and behind schedule.
b
The project is overbudget and ahead of schedule.
c
The project is underbudget and ahead of schedule.
d
The project is underbudget and behind schedule.
Question
Not yet answered
Marked out of
Flag question
Question text
The Dalron project is doing well, and no corrective action is needed?
Is it true or false?
Select one:
True
False
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock