Question: 14. Apply PERT Analysis to this project. Activity Optimistic Cost Realistic Cost Pessimistic Cost G 3000 4000 4800 H 8000 10000 12000 I 9000 14000
14. Apply PERT Analysis to this project.
| Activity | Optimistic Cost | Realistic Cost | Pessimistic Cost |
| G | 3000 | 4000 | 4800 |
| H | 8000 | 10000 | 12000 |
| I | 9000 | 14000 | 18000 |
| J | 7000 | 9700 | 10500 |
| K | 12000 | 15000 | 18900 |
| L | 13000 | 14200 | 15500 |
- What is the expected cost?
- What is the standard deviation of the cost? (round to 3 decimals)
- What is the probability of not exceeding the expected cost?
- What is the cost that wont be exceeded with probability of 0.94? (round to 2 decimals)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
