Question: 14. Developing input for the MPS that will fit current plant, equipment, and workforce limitations is the objective of a. Rough-cut Capacity Planning b. Detailed

14. Developing input for the MPS that will fit current plant, equipment, and workforce limitations is the objective of

a.

Rough-cut Capacity Planning

b.

Detailed Operations Planning

c.

Resource Requirements Planning

d.

Production Planning

8. Which of the following are suitable measures for capacity planning? I. dollars per year, II. standard hours

a.

I only

b.

Both I and II

c.

II only

d.

Neither I nor II

9. Referring to Table 8, the work center utilization for the work center for week 40 is

a.

92%

b.

72%

c.

90%

d.

80%

Work Center Information for Week 40

14. Developing input for the MPS that will fit

10. Referring to Table 7, if this assembly runs 5 days per week, 8 hours per day and you can put one worker at any station that can work at 130% of standard, how many products can be produced in a week?

a.

Less than 400 units.

b.

Greater than or equal to 500 but less than 600 units.

c.

Greater than or equal to 600 units.

d.

Greater than or equal to 400 but less than 500 units.

Assembly Line to Produce X2K4 Toy Robots

(Standard Time in Minutes)

14. Developing input for the MPS that will fit

50.0 2.5 2.5 5.0 36.0 hours scheduled hours absenteeism hours wait for tooling hours power failure standard hours of production output Station Standard Station Standard 1 2 3 4.2 4.5 4.0 4 5 6 2.5 2.7 3.0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!