Question: 1-4 Part question. PLEASE DO ALL 4 Profitability index Given the discount rate and the future cash flow of each project listed in the following
Profitability index Given the discount rate and the future cash flow of each project listed in the following table, use the Pito determine which projects the company should accept What is the PL of project A? (Round to two decimal places) Data table (Click on the following icon in order to copy its contents into a spreadsheet) Cash Flow Project A Project B Year 0 -$2,100,000 -$2,500,000 Year 1 $450,000 $1,250,000 Year 2 $600,000 1,100,000 Year 3 $750,000 $950,000 Year 4 $900.000 $800,000 Year 5 $1,050.000 $650,000 Discount rate 6% 18%