Question: (15 points) We have a single processor, and we are given a sequence of jobs with processing times t1,...,tn. Each job has to be processed

 (15 points) We have a single processor, and we are given

(15 points) We have a single processor, and we are given a sequence of jobs with processing times t1,...,tn. Each job has to be processed in a continious time interval, and these intervals cannot overlap. We want to minimize the average finishing times of these jobs. Prove that the optimal strategy is to process them in increasing order according to their processing times 2