Question: 15 With reference to the project graph below, the project is currently $7000 PV $6000 - ! AC ut of $5000 $4000 EV $3000 $2000

15 With reference to the project graph below, the
15 With reference to the project graph below, the project is currently $7000 PV $6000 - ! AC ut of $5000 $4000 EV $3000 $2000 $1000 Today Time Select one: O a. Behind schedule and under budget O b. Behind schedule and over budget O c. Ahead of schedule and over budget O d. Ahead of schedule and under budget